How Long Does an Apartment Renovation Take in Australia?

How Long Does an Apartment Renovation Take in Australia?
  • PublishedNovember 2, 2026

Most property owners ask the wrong question before they renovate.

They ask what materials cost. They ask about paint swatches. Then they sign a contract and discover that time is their actual enemy.

Every extra week of building means another week of paying rent somewhere else, paying mortgage interest, and managing logistics.

A standard apartment renovation in Australia takes between four weeks and six months from conception to handover. The physical work is only half the equation. The administrative work takes up the rest.

I have watched dozens of owners lose their patience because nobody told them how strata committees actually operate. If you understand the timeline before you sign an agreement, you stay in control of your budget and your sanity.

Here is the realistic timeline you need to plan for, broken down into clear stages.

Stage 1: Design and Strata Approvals (4 to 12 Weeks)

The clock starts before anyone touches a hammer.

In Australia, your apartment sits inside a shared building. You own the airspace inside your unit, but the building owns the common property. That includes the concrete slab beneath your tiles and the walls dividing your rooms.

You must plan for strata approval before you do anything else.

  • Cosmetic changes: Painting and minor carpet replacement often need no formal approval.
  • Minor renovations: Changing kitchen cabinets, installing floorboards, or swapping fixtures takes two to four weeks for committee review.
  • Major structural work: Moving wet areas, removing internal walls, or altering waterproofing requires a special resolution at a general meeting. This step alone takes six to twelve weeks.

The biggest mistake I see owners make is submitting incomplete paperwork. If your application lacks trade licences, insurance certificates, or scope diagrams, the committee will reject it. You will wait another month for the next meeting.

Professional teams handle this paperwork for you. For Sydney properties, Fine Touch Group coordinates directly with strata schemes. They have over thirty years of experience and more than one thousand completed projects, which gives them a high success rate with building managers. They know exactly what paperwork strata secretaries look for, preventing weeks of administrative delay.

Stage 2: Demolition and Rough-In (1 to 2 Weeks)

Once approval arrives, the physical work starts.

Demolition looks fast on television, but apartment buildings enforce strict rules. Most body corporates restrict noisy work to specific hours, often between nine in the morning and three in the afternoon on weekdays only. Weekend demolition is almost always banned.

1. Strip out old tiles, cabinetry, and flooring.

2. Transport rubble down elevators using protective covers.

3. Inspect exposed services for hidden water damage or electrical faults.

4. Run new plumbing pipes and electrical wiring inside the walls.

In an apartment, you cannot cut into concrete ceilings or floors without engineering checks. If your builder runs into surprises behind the plasterboard, expect a brief pause while they re-route services safely.

Stage 3: Waterproofing and Wet Areas (1 to 2 Weeks)

Waterproofing is the most critical phase of any Australian apartment update.

Water leaks do not just destroy your floor. They destroy the ceiling of the unit below you. If your waterproofing fails, strata can force you to rip out brand new tiles at your own expense.

Australian standards require strict drying times between liquid membrane coats. Good trades do not rush this process. They apply the first coat, wait twenty-four hours, apply the second coat, and let it cure completely before laying a single tile.

Fine Touch Group provides a six-year waterproofing warranty on their work. That level of backing gives you legal protection and genuine peace of mind. Their bathroom renovations start from twenty-eight thousand dollars, delivering proper waterproofing methods that satisfy building inspectors and strata bylaws alike.

Stage 4: Joinery, Tiling, and Stone (2 to 4 Weeks)

Once the wet areas cure, your apartment starts looking like a home again.

This phase includes:

  • Laying floor and wall tiles.
  • Installing custom joinery and built-in wardrobes.
  • Fitting kitchen cabinets and stone benchtops.
  • Installing doors, architraves, and skirting boards.

Custom cabinetry takes time to fabricate. A smart builder measures your space during the rough-in stage so the factory can build your kitchen while demolition finishes.

If you order stone benchtops, the stonemason cannot create accurate templates until the base cabinets sit level on your floor. Allow seven to ten working days between cabinet installation and stone delivery.

Fine Touch Group offers kitchen renovations starting from thirty-one thousand dollars, featuring custom cabinetry and stone benchtops with fixed-price clarity. Because they include a free three-dimensional model with every quotation, their team builds precisely to plan, avoiding measuring errors on site.

Stage 5: Painting, Fixtures, and Detailing (1 to 2 Weeks)

The final stage moves quickly, but requires high attention to detail.

  • Painters apply undercoats and topcoats to walls, ceilings, and trim.
  • Electricians install light fixtures, power outlets, and switches.
  • Plumbers fit taps, toilets, showerheads, and basins.
  • Flooring teams install engineered timber, hybrid boards, or carpet with certified acoustic underlay.

Never cut corners on acoustic underlay in an Australian apartment. Your strata committee will demand an acoustic certificate proving your new hard floors meet noise transfer rules.

The Overall Timelines by Project Scope

To give you a clear reference, here is the total physical build time you should expect:

  • Single room updates (bathrooms or kitchens): Three to five weeks of construction.
  • Whole apartment updates: Six to twelve weeks of construction.

For a full apartment overhaul encompassing living spaces, flooring, painting, joinery, and multiple wet areas, Fine Touch Group offers packages starting from eighty-five thousand dollars. Their transparent, itemised, fixed-price quotes mean you know the exact schedule and investment before work begins.

How to Keep Your Project on Schedule

Delays happen when communication breaks down between trades, suppliers, and building managers.

If you manage the project yourself, you must book the service elevator every day, schedule parking for trades, and coordinate deliveries through common property. Miss one lift booking, and your stone delivery gets turned away at the street.

I always advise property owners to work with a licensed builder who provides dedicated project management. Fine Touch Group coordinates every trade, handles scheduling, and provides remote updates if you live offsite during the build. They hold a New South Wales builder licence, which guarantees that an accountable specialist oversees every contractor on your site.

Plan your design early. Secure your strata approvals before buying materials. Work with contractors who understand apartment logistics. When you respect the process, your renovation finishes on time, within budget, and without headaches.